On this page:

The primary purpose of Lake Eildon is to provide a safe and secure water supply while offering some flood mitigation where possible.

During October 2022 the Goulburn River experienced major flooding, with flood waters causing significant damage to farms, townships, roads, water supply infrastructure and communities.

Following these floods, the Department of Energy, Environment and Climate Action (DEECA) engaged Hydrology and Risk Consulting (HARC) to undertake a technical assessment of Lake Eildon. The assessment was designed to determine if changing the operating arrangements could improve protection for downstream communities from future flooding and the associated financial and non-financial implications of such changes.

The assessment looks at 6 options for their potential to improve protection for downstream communities from future flooding. All options explored were found to be ineffective or unreliable as flood mitigation strategies, or created costs and impacts that outweigh the benefits of a change to how the storage is managed.

The assessment report highlights that tributaries that flow into the Goulburn River downstream of Lake Eildon have a more significant impact on flooding in communities downstream, including Molesworth and Seymour, than releases from the lake.

The Victorian Floodplain Management Strategy provides policy and guidance for investment in flood mitigation infrastructure and maintenance. The investment principles include cost effectiveness, so that the flood mitigation benefits are greater than the total cost (including both capital and ongoing costs).

A working group involving DEECA, local councils, water corporations, Goulburn Broken CMA and the Victorian Environmental Water Holder were involved in scoping and supporting the assessment.

What options have been looked at?

The technical assessment investigated 6 options as selected and agreed by the working group.

Option 1: Change target filling curves so that Lake Eildon is full later in the year (for example December/January instead of October/November) and under less conservative inflow statistics (for example, reaching full supply in 85 years out of a hundred instead of 95 years).

Option 2: Reduce target storage levels by holding the lake, where possible, at a maximum volume of 78%, 85%, 90%, 95% of Full Supply Level (FSL) all year round.

Option 3: Reduce target storage based on climate signals by holding the lake, where possible at a lower Full Supply Level based on industry-standard climate indicators indicating a wet year.

Option 4: Pre-release based on forecast rainfall by releasing water to create airspace within the lake, 2 to 3 days prior to forecast rainfall and resulting inflows.

Option 5: Change maximum surcharge by increase the amount of water that is held in the lake above the Full Supply Level during a flood.

Option 6: Restrict maximum outflows by restricting the outflows to match the minor, moderate or major flood class levels downstream of Lake Eildon, and allowing the reservoir to surcharge more often.

The scope of the assessment

The technical assessment provides important information on how changing the operating arrangements could improve protection for downstream communities from future flooding and the associated financial and non-financial implications of such changes.

The assessment of the options was split over two stages:

  • Stage 1: Assessments of the water resource implications, flood frequency changes at Lake Eildon, and anticipated changes to 1993 and 2022 peak outflows from Lake Eildon (if the events were repeated)
  • Stage 2: Detailed technical assessment of initial capital costs, upstream water level implications, flow regime changes, and potential reductions of tangible flood damages (only option 1 and 2 progressed to stage 2)

What the technical assessment tells us

The assessment was informed by applying existing water resource and flood hydrology models and using historical datasets. Results from the technical analyses completed are suitable for high-level comparisons between current conditions (base case) and what is anticipated if the options were implemented.

During the stage 1 assessment, options 3 to 6 were not deemed to be robust flood mitigation options and therefore not progressed to stage 2 for the following reasons:

  • Option 3: Reduce target storage based on climate signals. Climate signals tested for this were generally poor predictors of monthly inflows and storage volumes at Lake Eildon. This meant that – when combined with the influence of downstream flow constraints during wet periods – the option to reduce target storage based on climate signals was unlikely to increase the flood mitigation provided by Lake Eildon.
  • Option 4: Pre-release based on forecast rainfall. The uncertainty in the predicted location of where rainfall will be heaviest will constrain the degree to which storage operators can confidently make pre-releases without either reducing the water available to entitlement holders or making downstream flooding worse. Furthermore, the event-based analysis of the October 1993 and October 2022 floods showed that increasing pre-releases to the moderate flood class level flow threshold downstream of Lake Eildon exacerbated the peak flows estimated at Seymour.
  • Option 5: Change maximum surcharge. This option would increase the duration of Lake Eildon outflows above the minor, moderate and major flood classifications at Eildon as well as materially increase the likelihood of the dam overtopping during back-to-back floods.
  • Option 6: Restrict maximum outflows. This option would increase the duration of Lake Eildon outflows above the minor, moderate and major flood classifications at Eildon.

The two options that progressed to the detailed technical assessment were changing the target filling curve (option 1) and reducing the target storage (option 2). These options could increase the flood mitigation provided by Lake Eildon; however, the cost of offsetting supply reliability impacts outweighed the avoided flood damages.

The main reason for the low benefit to cost ratio is that the flood mitigation benefits provided by the changes to target filling curve (option 1) and reduced target storage (option 2) diminish the further downstream the flood frequencies are assessed. Namely, the degree of difference between the frequency estimates reduce by Molesworth, and the difference is then minor at Seymour.

This is because the tributary flows downstream of Eildon from the Rubicon River, Acheron River, Yea River, King Parrot Creek, Sugarloaf Creek and Sunday Creek influences the peak flows at towns such as Seymour. This means that changes to operations at Eildon have less influence on reducing the overall avoided damages downstream. In contrast, the approximate initial capital cost of water shares to implement these options ranges from $7.5 million to $266 million.

When looking at the 1993 and 2022 floods, the only option that would have made a difference to what was actually observed during these floods, would have been holding the storage to a reduced level of 78% FSL. However, this option still had a low cost to benefit ratio.

If option 1 or any other target storage within option 2 was implemented, there would have been no material difference to the flows observed downstream of Lake Eildon, Molesworth and Seymour.

The assessment also looked at other impacts from changing the filling curve (option 1) and reducing the volume of water stored in Lake Eildon (option 2). Both options would change the downstream flow regime in the Goulburn River, by reducing flows in generally wetter months and increasing them in drier months. This may have negative environmental impacts, though further investigation would be required to confirm this.

For option 2, there would also be some recreational impacts because the water body would be smaller and the distance between community and recreational facilities, for example holiday accommodation, and the water’s edge would increase.

Lake Eildon Technical Assessment Webinar

A live online public webinar was held on the evening of Tuesday 9 April 2024.

At the webinar, water resource engineers from HARC presented on the technical assessment findings and took questions, alongside a representative from DEECA.

What’s next?

The technical assessment does not identify any option at Lake Eildon which warrants further consideration. Whist the assessment did not identify any viable options for flood mitigation at Lake Eildon, the information gathered and outputs from this assessment are available to local councils and CMAs when delivering flood studies and reviewing flood mitigation options in their local area.

Flood studies are designed to help communities understand and manage their risk and the outputs often include preferred elements for Total Flood Warning Systems, for example improved flood warning service, preferred options for flood mitigation measures, draft planning scheme amendments and draft components of the Municipal Flood Emergency Plan.

The Victorian Government is committed to supporting local councils by investing in traditional funding streams such as the Risk and Resilience Grants Program and the Disaster Ready Fund, as well as providing an additional $10 million over the next 5 years to deliver flood studies in regional Victoria.

The Victorian Floodplain Management Strategy provides policy and guidance for investment in flood mitigation infrastructure and maintenance.

Post the completion of a flood study, if there is a preferred flood mitigation option, this can be put forward for funding consideration. The Victorian Government is guided by a set of principles when deciding whether to invest in the flood mitigation measure. The principles include due process, due diligence, supporting analysis, community benefit and cost effectiveness, being that the flood mitigation benefits are greater than the total cost (including both capital and ongoing costs).

The ongoing maintenance costs of flood mitigation infrastructure is the responsibility of the beneficiaries, who may be represented by Local Government Authorities (LGAs).

In addition to investing in flood studies in regional Victoria, DEECA have been analysing potential benefits and impacts of higher river flows on the Goulburn River as part of The Victorian Constraints Measures Program (CMP). The CMP, if implemented, would help those along the Goulburn River manage flooding up to the minor flood level.

The CMP is exploring how enhanced natural river flows could be delivered while managing risks and impacts to public and private land, infrastructure, stock, crops and people. The CMP is part of a wider initiative that makes the best use of available water for the environment and delivers it to where it is needed.

A feasibility study is considering how higher river flows (up to the minor flood level) might affect landholders along the river to better understand the programs benefits and impacts to the community if the program was to proceed. An important aspect to this work is looking at how landholders can be compensated for any impact they may have from these higher flows. The feasibility study’s findings will be used to inform an upcoming Murray-Darling Basin Authority-led roadmap for implementation that seeks to resolve cross-border issues.

Timelines and deliverables

Deliverable

Details

Timing

Scope development

Scoping document developed and reviewed by key stakeholders

March 2023 – June 2023

Independent consultant engaged to undertake assessment and prepare report

Deliver the assessment on the operating arrangement for Lake Eildon

July 2023 – March 2024

Lake Eildon Technical Assessment Report

Report published on DEECA website

March 2024

Public webinar

Public webinar on the findings of the Lake Eildon Technical Assessment

webinar link

9 April 2024
6.00 – 7.30pm

Background

Lake Eildon has operated to a set of filling targets during the winter and spring months since 1959.

The current filling curve has been in use since 2012, with the objective of filling the storage in 19 out of 20 years, to protect the reliability of water entitlements, while offering some flood mitigation.

Goulburn-Murray Water (GMW) is the storage manager for Lake Eildon.

The Bulk Entitlement (Eildon-Goulburn Weir) Conversion Order 1995 (Goulburn BE) prescribes how GMW is to harvest, store and supply water to its entitlement holders.

Lake Eildon’s full supply level is 288.9 m AHD, at which it holds 3,334,158 ML. In October 2022, inflows to Lake Eildon peaked at 145,000 ML/day while releases were able to be maintained at a peak of 38,000 ML/day.

There are no infrastructure constraints to the operating arrangement options currently identified. The outlet through the hydro-power station turbines has a maximum capacity of approximately 17,000 ML/day.

The gates on Lake Eildon Spillway are operational at 77% capacity, which is the top of the spill level of the spillway.

The GMW website provides more information on the flood event in October 2022.

Page last updated: 26/11/24